PRISM Project #13-1287 (Completed)
Nason Creek UWP Horseshoe Bend Acquisition
    Project Details    
Chelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #163290, Looking upstream, Alberg on left
Chelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition (#13-1287) Attachment #163290, Looking upstream, Alberg on left

Chelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #163290, Looking upstream, Alberg on left Chelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #163284, Gravel bar on CoakerChelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #163291, Old cabins on Alberg parcel  Merritt sideChelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #163292, Alberg on Merritt sideChelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #163293, Deep pool Alberg parcel on Hwy 2Chelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #163299, Old cabins on Coaker next to Nason CreekChelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #171138, P1140583Chelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #171139, P1140590Chelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #171140, P1140600Chelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #171141, P1140602Chelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #171142, P1140586Chelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #171143, P1140589Chelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #171144, P1140593Chelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #171145, P1140598Chelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #171146, P1140599Chelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #171442, Tree on right bank across from Crone beachChelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #180183, P1150037Chelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #180184, P1150038Chelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #180185, P1150039Chelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #180186, P1150040Chelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #180187, P1150043Chelan-Douglas Land Trust; Nason Creek UWP Horseshoe Bend Acquisition  (#13-1287)

Attachment #180188, P1150042
Project Status:  Closed Completed since 01/11/2018
 
Project Type:  Acquisition
Project Sponsor:  Chelan-Douglas Land Trust
Funding Board:  Salmon Recovery Funding Board
              Funding  
Salmon Federal Projects: $332,601
Total RCO Grant: $332,601 (85%)
Sponsor Match: $58,704 (15%)
Total Agreement: $391,305 (100%)
              Links
 

    Project Description    
The Chelan-Douglas Land Trust is partnering with private landowners to acquire and with Chelan County to protect existing high quality riparian habitat and provide public access to Nason Creek, a tributary of the Wenatchee River, which flows into the Columbia River. This reach of Nason Creek has a high percentage of the endangered spring Chinook and steelhead spawning in all of Nason Creek, which in turn has a high percentage in the entire Wenatchee basin.   CDLT will acquire approximate approximately 12.3 acres and .37 miles of streambank.   Nason Creek is a Category 2 stream, a major spawning area for spring Chinook and steelhead and a core area for bull trout, and is the highest priority in the Wenatchee Basin for both Protection and Restoration.   Chelan County owns  22 acres contiguous to the parcels to be acquired, which it intends to manage in cooperation with this protection project.   Reassembling these subdivided properties will result in permanent protection, enable clean-up of derelict structures and debris,   create public access to Nason Creek, and will enable implementing future habitat restoration actions appropriate to this site.  The existing private landowners have been unwilling to agree to restoration.

    Project Contacts    
         
Project Sponsor: Chelan-Douglas Land Trust Lead Entity: Upper Columbia Salmon Recovery Board Lead Entity
  Project Contact: Mickey Fleming
mickey@cdlandtrust.org
(509) 667-9708
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Amee Bahr
Amee.Bahr@rco.wa.gov
(360) 867-8585
   

    Project Location    
General Area:   Upper White Pine reach of Nason Creek.
County:   Chelan
Legislative District:   12
Congressional District 2022:   08
Salmon Recovery Regions:   Upper Columbia River
Watershed Administrative Unit:   Lower Nason
Watershed Administrative Unit:   Upper Nason
HUC8:   Wenatchee (17020011)
WRIA:   Wenatchee
Sections:   03
Sections:   04
Township:   T26NR16E
Coordinates:   47.78361562
-120.84467735

    Worksites    
Worksite NameScope of Work
Upper White Pine (#1) Administrative costs (Acq), Appraisal, Appraisal Review, Baseline Documentation, Closing, Recording, Taxes, Title, Cultural resources (Acq), Demolition, Environmental Audits, Land, Noxious weed control, Standard Incidentals, Stewardship plan, Survey (Acq), Wetland Delineations
  
Amounts may not be complete

    Properties    
Worksite Name Property Name Actual Acquisition
Acres
Actual Acquisition
Cost
Upper White Pine (#1)   Property 1 - Private Landowner 2.00 $174,063
Upper White Pine (#1)   Property 2 - Private Landowner 10.29 $218,805
   Total12.29$392,868
Amounts may not be complete

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 12/04/2013
Progress Report Due 06/30/2014
Annual Project Billing Due 07/31/2014
Order Appraisal(s) 09/30/2014
Progress Report Due 12/31/2014
Order Appraisal Review(s) 01/01/2015
Cultural Resources Complete 04/01/2015
Environmental Assess Complete 06/30/2015
Progress Report Due 06/30/2015
Annual Project Billing Due 07/31/2015
Purchase Agreement Signed 09/18/2015 Alberg completed. Coaker awaits resolution of estate.
Recorded Acq Documents to RCO 10/30/2015
Recorded Land Survey to RCO 10/30/2015
Acquisition Closing 11/30/2015 Alberg
Progress Report Due 12/31/2015
Progress Report Due 09/30/2017
Demolition Complete 12/31/2017
Noxious Weed Control Complete 12/31/2017
Funding Acknowl Sign Posted 12/31/2017
Agreement End Date 12/31/2017
Stewardship Plan to RCO 03/31/2018
Final Report Due 03/31/2018
Final Billing Due 03/31/2018


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State 13-1287 Project Agreement.pdf 04/10/2014
Amendment - State 13-1287 Amend #3 Cost Change.pdf 09/19/2017
Amendment - State 13-1287 Amend #2 Time Ext.pdf 05/31/2017
Amendment - State 13-1287 Amend #1 Time Extension.pdf 04/19/2016
Amendment request UWP Cost Increase Request 7.24.17.pdf 12/05/2017
Billing Expanded Documentation Nason Cr invoice paid to Chelan County Natural Resource Dept.pdf 02/01/2017
Billing forms 13-1287 Billings 1-3.pdf 09/19/2019
Certification of Applicant Match Icicle LAF Approval Alberg-Coaker 03.16.15.pdf 04/14/2015
Correspondence Alberg Just Compensation Reloc 11-03-15.pdf 11/05/2015
Cost Estimate Appendix C Cost Estimate.pdf 05/30/2013
Deed AFN 2466380 Coaker SWD 10-06-17.pdf 10/12/2017
Deed AFN 2427897 Deed Alberg to CDLT 11.05.15.pdf 11/09/2015
Deed of right AFN 2466722 Coaker DOR 10-12-17.pdf 10/17/2017
Deed of right AFN 2427897 Alberg Deed of Right 12-10-15.pdf 12/10/2015
Deed or title Quit Claim Deed to Chelan County 12-30-02.pdf 09/24/2013
Environmental Site Assessment Report Alberg - Phase I Environ Assess 07-03-15.pdf 07/06/2015
Environmental Site Assessment Report Coaker - Phase I Environ Assess 06-27-15.pdf 07/06/2015
Final project report Final Report, 13-1287 (accepted 01/10/18 15:45:44).pdf 01/10/2018
Hazardous Substance Certification Form Coaker Hazard Substanc Certific 8.23.17.pdf 01/10/2018
Hazardous Substance Certification Form Coaker RCO_Hazardous_Substances_Certification.doc 08/23/2017
Hazardous Substance Certification Form Alberg Haz Sub Certif 10-22-15.pdf 10/22/2015
Map Appendix A Map 2 Floodplain Wetland Spawning.pdf 05/02/2013
Map Appendix A Map 1 VIcinity.pdf 05/02/2013
Map: Parcel map Appendix A Map 3 Parcel Map.pdf 05/02/2013
Photo P1150042.jpg 03/17/2014
Photo P1150043.jpg 03/17/2014
Photo P1150040.jpg 03/17/2014
Photo P1150039.jpg 03/17/2014
Photo P1150038.jpg 03/17/2014
Photo P1150037.jpg 03/17/2014
Photo Tree on right bank across from Crone beach.jpg 08/20/2013
Photo P1140599.jpg 08/19/2013
Photo P1140598.jpg 08/19/2013
Photo P1140593.jpg 08/19/2013
Photo P1140589.jpg 08/19/2013
Photo P1140586.jpg 08/19/2013
Photo P1140602.jpg 08/19/2013
Photo P1140600.jpg 08/19/2013
Photo P1140590.jpg 08/19/2013
Photo P1140583.jpg 08/19/2013
Photo Old cabins on Coaker next to Nason Creek.jpg 05/02/2013
Photo Deep pool Alberg parcel on Hwy 2.jpg 05/02/2013
Photo Alberg on Merritt side.jpg 05/02/2013
Photo Old cabins on Alberg parcel Merritt side.jpg 05/02/2013
Photo Looking upstream, Alberg on left.jpg 05/02/2013
Photo Gravel bar on Coaker.jpg 05/02/2013
Progress report Progress Report, 13-1287 (accepted 10/04/17 09:08:14).pdf 10/04/2017
Progress report Progress Report, 13-1287 (accepted 06/21/17 14:40:08).pdf 06/21/2017
Progress report Progress Report, (accepted 02/14/17 14:50:51).pdf 02/14/2017
Progress report Progress Report 10/09/2015.pdf 10/09/2015
Progress report Progress Report 12/02/2014.pdf 12/02/2014
Project Application Report Application Report, 13-1287A (submitted 08/12/13).pdf 08/12/2013
Salmon Project Proposal Final Proposal without Track Changes.pdf 07/12/2013
Salmon Project Proposal Final Proposal with Track Changes.pdf 07/12/2013
Salmon Project Proposal Horseshoe Bend Draft Application Packet.pdf 05/07/2013
SRFB Review Panel Comment Form 13-1287 2013 Review Panel Final Comments.doc 05/07/2014
SRFB Review Panel Comment Form Appendix_G1_Response_Early_Review 13-1287.doc 08/20/2013
Stewardship plan Nason Creek Steward Plan Jan 2018.pdf.pdf 01/17/2018

Back to top Date of last change: 03/18/2025