Fishery Pt Neighborhood Shoreline CE Acquisition
|
    Funding |
  |
|
    Links |
  |
|
|
The goal of this acquisition project is to protect the natural shoreline processes, natural habitat, water quality, and native shoreline vegetation of the target property at Fishery Pt., Waldron Island for endangered outmigrating juvenile Chinook salmon; juvenile chum and pink salmon; surf smelt; Pacific sand lance; and Pacific herring. This acquisition project will protect the target property through purchase of two Conservation Easements and donation of an additional two Conservation Easements with up to three development rights to ensure permanent protection of over 40 acres and 3,000 feet of natural shoreline on Waldron Island. It is located in the highest priority fish use region and highest priority salmon recovery region in the San Juan Islands. This highest priority property extends along the north shore of Waldron Island both east and west of Fishery Pt. East of Fishery Pt. the medium bank shoreline is characterized by a mixed conifer forest including old growth Douglas fir and an herbaceous understory of native marine riparian vegetation. West of Fishery Pt. the low/no bank “sandflat” extends over 200 ft. inland and is discontinuously vegetated with sedges, herbaceous plants and a few trees. This project will add to existing Conservation Easement and Preserve protection on Waldron Island for a total of approximately 6 miles of shoreline and 800 acres of natural habitat protected by the San Juan Preservation Trust.
|
General Area:
|
|
Waldron Island
|
County:
|
|
San Juan
|
Legislative District:
|
|
40
|
Congressional District 2022:
|
|
02
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Waldron Island
|
HUC8:
|
|
San Juan Islands (17110003)
|
WRIA:
|
|
San Juan
|
Sections:
|
|
11
|
Township:
|
|
T37NR03W
|
Coordinates:
|
|
48.71660736 -123.04364658
|
|
|
Worksite Name | Scope of Work |
San Juan Islands WRIA 2 (#1)
|
Administrative costs (Acq), Appraisal, Appraisal Review, Closing, Recording, Taxes, Title, Easement
|
| |
Amounts may not be complete
Worksite Name | | Property Name | | Actual Acquisition Acres | Actual Acquisition Cost |
San Juan Islands WRIA 2 (#1)
|
|
Property 1 - Private Landowner
|
|
23.66
|
$206,726
|
San Juan Islands WRIA 2 (#1)
|
|
Property 2 - Private Landowner
|
|
0.00
|
$1,760
|
San Juan Islands WRIA 2 (#1)
|
|
Property 3 - Private Landowner
|
|
0.00
|
$14,032
|
San Juan Islands WRIA 2 (#1)
|
|
Property 4 - Private Landowner
|
|
0.00
|
$5,998
|
| | | Total | 23.66 | $228,516 |
Amounts may not be complete
Milestone Name | Target Date | Description |
Project Start
|
09/18/2014
|
SRFB funding award date
|
Order Appraisal(s)
|
11/15/2014
|
Two Northern Lights LLC & CT Burn Properties
|
Baseline Documentation to RCO
|
12/20/2014
|
Two Northern Lights LLC & CT Burn Properties
|
Environmental Assess Complete
|
12/20/2014
|
Two Northern Lights LLC & CT Burn Properties
|
Acquisition Closing
|
12/31/2014
|
Two Northern Lights LLC & CT Burn Properties
|
Order Appraisal Review(s)
|
01/15/2015
|
Two Northern Lights LLC & CT Burn Properties
|
Progress Report Due
|
01/31/2015
|
|
Recorded Acq Documents to RCO
|
03/31/2015
|
Two Northern Lights LLC & CT Burn Properties
|
Stewardship Plan to RCO
|
03/31/2015
|
Two Northern Lights LLC & CT Burn Properties
|
Order Appraisal(s)
|
03/31/2015
|
Burn Family Trust & Wernstedt Properties
|
Order Appraisal Review(s)
|
06/30/2015
|
Burn Family Trust & Wernstedt Properties
|
Progress Report Due
|
06/30/2015
|
|
Annual Project Billing Due
|
07/31/2015
|
|
Progress Report Due
|
12/31/2015
|
|
Progress Report Due
|
03/31/2016
|
|
Annual Project Billing Due
|
07/31/2016
|
|
Progress Report Due
|
08/31/2017
|
|
Purchase Agreement Signed
|
11/30/2017
|
Burn Family Trust CE
|
Baseline Documentation to RCO
|
11/30/2017
|
Burn Family Trust CE
|
Environmental Assess Complete
|
11/30/2017
|
Burn Family Trust CE
|
Progress Report Due
|
11/30/2017
|
|
Acquisition Closing
|
12/31/2017
|
Burn Family Trust CE
|
Recorded Acq Documents to RCO
|
12/31/2017
|
Burn Family Trust CE
|
Stewardship Plan to RCO
|
12/31/2017
|
Burn Family Trust CE
|
Purchase Agreement Signed
|
03/31/2018
|
Wernstedt CE
|
Environmental Assess Complete
|
03/31/2018
|
Wernstedt CE
|
Baseline Documentation to RCO
|
04/30/2018
|
Wernstedt CE
|
Progress Report Due
|
04/30/2018
|
|
Acquisition Closing
|
05/31/2018
|
Wernstedt CE
|
Agreement End Date
|
06/30/2018
|
|
Recorded Acq Documents to RCO
|
06/30/2018
|
Wernstedt CE
|
Stewardship Plan to RCO
|
06/30/2018
|
Wernstedt CE
|
Final Report Due
|
07/31/2018
|
|
Final Billing Due
|
08/31/2018
|
|