Crescent Harbor Creek Restoration Design & Permit
    Project Details    
Project Status:  Closed Completed since 10/18/2017
 
Project Type:  Planning
Project Sponsor:  Skagit River System Cooperative
Funding Board:  Salmon Recovery Funding Board
              Funding  
Puget Sound Acq. & Restoration: $0
Salmon Federal Projects: $55,142
Total RCO Grant: $55,142 (85%)
Sponsor Match: $9,731 (15%)
Total Agreement: $64,873 (100%)
              Links
 

    Project Description    
We propose to use SRFB funds to develop a preliminary restoration design and acquire construction permits for lower Crescent Harbor Creek, a tributary to the Crescent Harbor Salt Marsh restoration site on northern Whidbey Island. The project is intended to restore the historic floodplain alignment, reduce stream velocity to increase fish access and improve water quality, and restore native wetland hydrology in lower Crescent Harbor Creek.
Goals for the project are to:
1. Sustainably restore natural stream and floodplain processes, conditions, functions, and biological responses.
2. Restore riparian and scrub-shrub wetland habitats.
3. Restore non-natal stream channel rearing capacity and freshwater nearshore inputs for ESA-listed juvenile Chinook salmon during the early phases of their oceanward migration.
4. Restore channel spawning habitat capacity for adult coho salmon.
5. Restore estuarine and wetland habitat conditions for other native fish and wildlfe species.
6. Improve water quality conditions within lower Crescent Harbor Creek and the Crescent Harbor Salt Marsh, a 206 acre SRFB- and ESRP-funded estuary restoration site located at the mouth of Crescent Creek.
Matching funds, in the form of staff time for design review and for securing the permits necessary for project construction, will be provided by the US Navy.

    Project Contacts    
         
Project Sponsor: Skagit River System Cooperative Lead Entity: Island County Lead Entity
  Project Contact: Devin Smith
dsmith@skagitcoop.org
(360) 391-1984
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Bridget Kaminski
bridget.kaminski@rco.wa.gov
(360) 472-5546
   

    Project Location    
General Area:   Oak Harbor
County:   Island
Legislative District:   10
Congressional District 2022:   02
Salmon Recovery Regions:   Puget Sound
Watershed Administrative Unit:   Whidbey Island
HUC8:   Puget Sound (17110019)
WRIA:   Island
Sections:   36
Township:   T33NR01E
Coordinates:   48.30638541
-122.61998748

    Worksites    
Worksite NameScope of WorkActual Planning Cost
Lower Crescent Harbor Creek Property (#1) Cultural resources, Final design and permitting (B.1.b.11.a RCO), Preliminary design (B.1.b.11.a RCO) $70,026
 Total$70,026
Amounts may not be complete

    Properties    
Worksite Name Property NameLandowner Type
Lower Crescent Harbor Creek Property (#1)   Property 1 - P43358 Federal Government
   Total
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricFinal

Restoration Metrics (rolled up from Worksite level)

      
Area Encompassed (acres) (B.0.b.1) 30.0
Miles of Stream and/or Shoreline Affected (B.0.b.2) 0.28

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 03/01/2014
Data Gathering Started 03/01/2014
Annual Project Billing Due 07/31/2014
Progress Report Due 08/01/2014
Progress Report Due 11/30/2014
Progress Report Due 07/31/2015
Preliminary Design to RCO 03/31/2016
Progress Report Due 03/31/2016
Applied for Permits 05/31/2016
Cultural Resources Complete 12/30/2016
Progress Report Due 12/30/2016
Special Conditions Met 06/30/2017
Permits Complete 06/30/2017
Agreement End Date 06/30/2017
Final Report Due 09/30/2017
Final Billing Due 09/30/2017


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State 13-1112 Project Agreement.pdf 05/27/2014
Amendment - State 13-1112 Amend #6 Cost Change.pdf 08/15/2017
Amendment - State 13-1112 Amend #5 Cost Change.pdf 05/24/2017
Amendment - State 13-1112 Amend #3 Scope Change.pdf 06/30/2016
Amendment - State 13-1112 Amend #4 Time Extension.pdf 06/15/2016
Amendment - State 13-1112 Amend #2 Cost Change.pdf 08/11/2015
Amendment - State 13-1112 Amend #1 Time Extension.pdf 06/23/2015
Amendment request Final Design Amend Request 06-2016.docx 11/17/2016
Correspondence Site Visit,Crescent Harbor Creek Rest. Design &Permit13-1112.pdf 04/01/2013
Correspondence NASWI CO Support Letter.pdf 03/26/2013
Cost Estimate Revised Cost Estimate.xlsx 06/05/2013
Cost Estimate Crescent Harbor Creek Cost Estimate.xlsx 03/26/2013
Design document CHC Restoration Drawings 06-23-16.pdf 10/05/2017
Environmental Site Assessment Report Extract from Navy Mitigation Feasibility Report.pdf 06/05/2013
Final project report Final Report, 13-1112 (accepted 10/17/17 09:02:40).pdf 10/17/2017
Landowner acknowledgement form Landowner Acknowledgement Form.pdf 06/05/2013
Map Crescent Creek Locator Map.pdf 03/26/2013
Map: Area of Potential Effect (APE) Crescent Creek Site & APE Map.pdf 03/26/2013
Map: Planning Area Crescent Harbor-Creek Vicinity Map-Ortho.pdf 02/02/2016
Photo Crescent Harbor Creek Current Mouth 2.jpg 03/26/2013
Photo Crescent Harbor Creek Historic Mouth 1.jpg 03/26/2013
Photo Crescent Harbor Creek Diked Reach 2.jpg 03/26/2013
Photo Crescent Harbor Creek Culvert.jpg 03/26/2013
Photo Crescent Harbor Creek Historic Alignment.jpg 03/26/2013
Photo Crescent Harbor Creek Diked Reach 1.jpg 03/26/2013
Progress report Progress Report 12/09/2016.pdf 12/09/2016
Progress report Progress Report 02/02/2016.pdf 02/02/2016
Progress report Progress Report 08/11/2015.pdf 08/11/2015
Progress report Progress Report 02/27/2015.pdf 02/27/2015
Progress report Progress Report 12/19/2014.pdf 12/19/2014
Progress report Progress Report 07/18/2014.pdf 07/18/2014
Project Application Report Application Report, 13-1112P (submitted 08/16/13).pdf 08/16/2013
Project Support / Concern Documents Appendix_G1_Response_Early_Review.doc 06/24/2013
Project Support / Concern Documents Responses to Reviewer Comments- Crescent Harbor Creek.docx 06/05/2013
Salmon Project Proposal Revised Project Proposal.doc 06/05/2013
Salmon Project Proposal Project Proposal.pdf 03/26/2013
SRFB Review Panel Comment Form (13-1112) 2013 Final Review Panel Comments.doc 04/29/2014

Back to top Date of last change: 12/05/2024