Project Snapshot
PRISM Project #17-1304 (Completed)
Asotin IMW Monitoring 2017
    Project Details    
Project Status:  Closed Completed since 02/14/2022
 
Project Type:  Monitoring
Project Sponsor:  Asotin County Conservation District
Funding Board:  Salmon Recovery Funding Board
              Funding  
Salmon Federal Activities: $150,110
Total RCO Grant: $150,110 (85%)
Sponsor Match: $26,890 (15%)
Total Agreement: $177,000 (100%)
              Links
 

    Project Description    
The Asotin County Conservation District is requesting funding is to support ongoing monitoring in the Asotin Creek Intensively Monitored Watershed project (Asotin IMW). The project was started in 2008 and is expected to run until 2019. The funds are being requested to support i) juvenile steelhead PIT tagging and mark-recapture surveys and replace damaged PIT tag array equipment, and ii) habitat monitoring using the Columbia Habitat Monitoring protocol (CHaMP). These two monitoring efforts are being used to assess the effectiveness of large woody debris restoration at increasing juvenile productivity in Asotin Creek. Three tributaries in Asotin Creek need to be monitored: Charley Creek, North Fork Asotin Creek, and South Fork Asotin Creek. extent of fish monitoring is 12 sites 300-500 m in length, 4 in each tributary (see attached map). The extent of the habitat monitoring is 12 CHaMP sites (length 160-200 m) in Charley and North Fork Creek – Tetra Tech is funding CHaMP monitoring in South Fork Creek in 2017. This project will support the ESA listed summer steelhead recovery. All of the fish and habitat data collected will be made publically available in the PTAGIS (ptagis.org) and on the CHaMP website (champmonitoring.org). Analyses of the data will be conducted with other funds provided to the Asotin IMW by PSMFC.

    Project Contacts    
         
Project Sponsor: Asotin County Conservation District Lead Entity: Snake River Salmon Recovery Board Lead Entity
  Project Contact: Megan Stewart
megan@asotincd.org
(509) 552-8100
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Jeannie Abbott
Jeannie.Abbott@gsro.wa.gov
(360) 480-2701
   

    Worksites    
Worksite NameScope of WorkActual Monitoring Cost
Asotin (#1) Intensively monitored watershed (E.1.c.15) $177,000
 Total$177,000
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricFinal

Restoration Metrics (rolled up from Worksite level)

Monitoring
      Intensively monitored watershed (E.1.c.15)
# acres (to nearest 0.1 acre) Intensively monitored watershed (E.1.c.15.c) 1000.0
# miles (to nearest 0.01 mile) Intensively monitored watershed (E.1.c.15.a) 22.00

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 01/19/2018
Progress Report Due 06/15/2018
Annual Project Billing Due 06/30/2018
Special Conditions Met 12/31/2018 annual report due to the Monitoring Panel by this date (report can also be progress report for same time frame for PSMFC)
Other 05/01/2021 revising the scope to "monitoring AND restoration"
Annual Project Billing Due 06/30/2021
Progress Report Due 12/23/2021
Special Conditions Met 12/31/2021 annual report due to the Monitoring Panel by this date (report can also be progress report for same time frame for PSMFC) AND Final Report for PRISM
Agreement End Date 03/31/2022 time extension agreement end date if requested by sponsor
Final Report Due 04/15/2022
Final Billing Due 04/30/2022


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State Agreement.pdf 04/09/2018
Amendment - State 17-1304 Amendment #6 - Time Extension.pdf 12/17/2021
Amendment - State 17-1304 Amendment #5 - Asotin IMW Monitoring 2017.pdf 06/10/2021
Amendment - State 17-1304 Amendment #4 - Asotin IMW Monitoring 2017.pdf 04/05/2021
Amendment - State Amend 3 Time.pdf 06/11/2020
Amendment - State Amend 2 Time.pdf 12/11/2019
Amendment - State 17-1304 Amend #1 Special Conds.pdf 04/05/2019
Application Document Loughin 2010 -Asotin IMW Power Analysis.docx.docx 09/29/2017
Application Document srfb app auth.pdf 08/11/2017
Application Document IMW Certification Memo.pdf 08/08/2017
Application Review Report Application Review Report, 17-1304M(compl 08/14/17 15:23:25).pdf 08/14/2017
Application Review Report Application Review Report, 17-1304M(rtnd 08/08/17 13:42:33).pdf 08/08/2017
Correspondence 17-1304_AsotinIMW_Monitoring Panel questions.docx 09/28/2017
Cost Estimate Copy of AsotinIMW_ScopeOfWorkreved budget_2021_17-1304_v1.xlsx 04/13/2021
Cost Estimate AsotinIMW_ScopeOfWorkWork_FY2017_Aug9edit.xlsx 08/10/2017
Final project report Final Report, 17-1304 (accepted 12/23/21 09:18:46).pdf 12/23/2021
Final project report Final_Design_&_As-built_Report_IncreaseWoodDensity_17-1304.p.pdf 11/22/2021
Monitoring activity 17-1304_Asotin IMW Regional Monitoring Comment Form.pdf 10/10/2017
Progress report Progress Report, 17-1304 (accepted 02/12/21 12:24:31).pdf 02/12/2021
Progress report Progress Report, 17-1304 (accepted 01/06/20 11:10:19).pdf 01/06/2020
Progress report Progress Report, 17-1304 (accepted 01/25/19 09:30:42).pdf 01/25/2019
Project Application Report Application Report, 17-1304M (submitted 08/10/17 11:11:23).pdf 08/10/2017
Project Application Report Application Report, 17-1304M (submitted 08/08/17 11:52:10).pdf 08/08/2017
Salmon Project Proposal C4-Monitoring_AsotinIMW_2017.docx 08/08/2017
Scope of work ACDAmendment_17-1304_AsotinIMW.docx 03/08/2021
Scope of work AsotinCreekIMW_RevisedStudyPlan_2015.pdf 05/11/2017
SRFB Review Panel Comment Form 17-1304_AsotinIMW_Monitoring Panel questions_SBresponse.docx.docx 09/29/2017
Visuals 3 map 2.pdf 05/11/2017
Visuals 3 map 1.pdf 05/11/2017

Back to top Date of last change: 06/30/2023