Meadowdale: Informing Coastal Stream Restoration
|
Project Status:  |
Active since 03/26/2024 |
Planned Completion: |
11/30/2025
This project is in progress. Project scope, activities, and dollars may change.
|
Project Type:  |
Planning |
  |
|
Funding Board:  |
Recreation and Conservation Office
|
    Funding |
  |
|
    RCO Grant Status
|
  |
Total RCO Grant:
|
$139,821.00
|
|
Paid To Date:
|
$562.84
|
(0%)
|
Grant Balance:
|
$139,258.16
|
(100%)
|
|
    Links |
  |
|
|
The Tulalip Tribes and partners will investigate the ecological and geomorphic outcomes of the Meadowdale Park estuary restoration project in Edmonds, WA (RCO project number 18-1259) to inform the siting and design of future coastal stream mouths. The restoration project is the first stream mouth restoration project along the railroad corridor. The restoration included novel elements of excavating a large estuary embayment with room for the site to adjust to fluvial and coastal processes, as well as sea level rise. The proposed investigation will inform the onsite and offsite benefits of restored sediment transport conditions, as well as the sustainability of the estuary design.
|
Worksite Name | Scope of Work | Proposed Planning Cost |
Meadowdale Beach Park (#1)
|
Agency Indirect, Purchase miscellaneous equipment, Regional Feasibility and Pre-Design (Learning) Project
|
$200,139
|
| Total | $200,139 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Meadowdale Beach Park (#1)
|
|
Property 1 - Snohomish County
|
Local Government
|
| | | Total |
Amounts may not be complete
Milestone Name | Target Date | Description |
Data Gathering Begins
|
10/15/2020
|
Aerial imagery acquisition (UAV flights)
|
Data Gathering Begins
|
10/19/2020
|
Beach & Embayment Transects
|
Data Gathering Begins
|
10/19/2020
|
Sediment mapping and classification
|
Data Gathering Begins
|
03/02/2022
|
Fish sampling
|
Data Gathering Begins
|
11/20/2022
|
Time-lapse camera installation and maintenance
|
Data Gathering Begins
|
02/01/2023
|
Snohomish County Data Collection and Analysis
|
Data Gathering Begins
|
02/16/2023
|
Water quality data logger installation and maintenance
|
Project Start
|
07/01/2023
|
|
Cultural Resources Complete
|
07/01/2023
|
|
Progress Report Due
|
05/06/2024
|
|
Learning Plan to RCO
|
05/31/2024
|
Draft Plan to ESRP Science Coordinator
|
Data Gathering Begins
|
06/28/2024
|
Invertebrate Sampling
|
Annual Project Billing Due
|
07/31/2024
|
|
Wiki: Enter Initial Content
|
08/15/2024
|
|
Data Gathering Begins
|
09/01/2024
|
Biological Sample Analysis
|
Progress Report Due
|
10/09/2024
|
|
Learning Plan to RCO
|
10/31/2024
|
Final Plan attached to PRISM and wiki
|
Other
|
10/31/2024
|
Convene Technical Advisory Group Meeting to meet quarterly
|
Other
|
11/30/2024
|
Quarterly TAG meeting
|
Data Gathering Begins
|
12/31/2024
|
RFID PIT Tagged gravel tracking
|
Other
|
02/01/2025
|
Quarterly TAG meeting
|
Progress Report Due
|
04/01/2025
|
|
Other
|
05/01/2025
|
Quarterly TAG meeting
|
Interim Data Summary to RCO
|
07/15/2025
|
Deliverable 5.1: Attach Interim Results Analysis to PRISM and wiki
|
Annual Project Billing Due
|
07/31/2025
|
|
Other
|
08/01/2025
|
Quarterly TAG meeting
|
Other
|
08/31/2025
|
Deliverable 4.1: Data collection log
|
Draft Plan/Study Report
|
09/01/2025
|
Deliverable 6.1: Draft report to ESRP science coordinator
|
Final Plan/Study Report
|
10/15/2025
|
Deliverable 6.2: Attach to PRISM and wiki
|
Other
|
10/15/2025
|
Presentation Title, planned webinar date and venue (if applicable) of the presentation
|
Final Plan/Study Report
|
10/15/2025
|
Summary Report – Provide short summary restoration recommendations and guidance report for small coastal streams along the waterfront railroad corridor. Attach to PRISM and wiki.
|
Final Report Due
|
10/31/2025
|
|
Webinar: Present Study Results
|
11/20/2025
|
Attach slides to wiki and PRISM
|
Wiki: Finalize Content
|
11/30/2025
|
|
Agreement End Date
|
11/30/2025
|
PROJECT CLOSING. All expenditures must be prior to this date.
|
Final Billing Due
|
01/31/2026
|
|
NOTE: This data is subject to change.