Edmonds Marsh Estuary Restoration Design
|
    Funding |
  |
Salmon State Projects:
|
$450,000
|
|
Total RCO Grant:
|
$450,000
|
(85%)
|
Sponsor Match:
|
$80,000
|
(15%)
|
Total Agreement:
|
$530,000
|
(100%)
|
|
    Links |
  |
|
|
City of Edmonds will develop a preliminary design to reconnect the 28-acre Edmonds Marsh to Puget Sound, restoring uninterrupted juvenile fish passage to this barrier estuary, located adjacent to the city's downtown core. Restoration designs will include a new tidal channel, and in-stream and riparian habitat enhancements. The design effort will include continued communications with landowners within the restoration area, primarily Washington Department of Transportation-Ferries Division, slated to be the future owner of the Unocal Property. This future estuary restoration project addresses a key salmon recovery issue of limited juvenile access to important, yet rare, nearshore rearing habitat. Once constructed (in a future phase) the project will enable juvenile fish passage to rearing habitat for out-migrating Chinook, coho, chum and pink salmon to an area that is currently inaccessible to fish, increasing nearshore habitat diversity available along the highly degraded WRIA 8 nearshore. This RCO funding request will complete preliminary design, but the City is leveraging other funding sources to ensure a full design can be completed without additional funding requests of RCO. The project restores a essential lost estuary connection and valuable fish habitat, but also has the unique condition in that it can actually add new aquatic habitat (in upland Shellabarger Marsh) when combined with the advent of sea-level rise. Designs will meet standards of Manual 18 Appendix D-2.
|
County:
|
|
Snohomish
|
Legislative District:
|
|
21
|
Congressional District 2022:
|
|
02
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Possession Sound-N Elliot Bay
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Cedar - Sammamish
|
Sections:
|
|
26
|
Township:
|
|
T27NR03E
|
Coordinates:
|
|
47.80654868 -122.38822725
|
|
|
Worksite Name | Scope of Work | Proposed Planning Cost |
Edmonds Marsh & Nearshore (#1)
|
Cultural resources, Preliminary design (B.1.b.11.a RCO)
|
$530,000
|
| Total | $530,000 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Edmonds Marsh & Nearshore (#1)
|
|
Property 1 - BNSF Right-of-way
|
Private
|
Edmonds Marsh & Nearshore (#1)
|
|
Property 2 - Edmonds Marsh
|
Local Government
|
Edmonds Marsh & Nearshore (#1)
|
|
Property 3 - Marina Beach Park
|
Local Government
|
Edmonds Marsh & Nearshore (#1)
|
|
Property 4 - Unocal property
|
Private
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Estimated |
Restoration Metrics (rolled up from Worksite level) |
|
|
|
Area Encompassed (acres) (B.0.b.1)
|
28.0
|
|
Miles of Stream and/or Shoreline Affected (B.0.b.2)
|
0.25
|
Permit Type | Applied Date | Received Date | Expiration Date | Permit Number |
Water Quality Certification [Section 401]
|
|
|
|
|
Shoreline Permit
|
|
|
|
|
SEPA
|
|
|
|
|
Hydraulics Project Approval [HPA]
|
|
|
|
|
Dredge/Fill Permit [Section 10/404 or 404]
|
|
|
|
|
Cultural Assessment [Section 106]
|
|
|
|
|
Clear & Grade Permit
|
|
|
|
|
Archeological & Cultural Resoures (EO 05-05)
|
|
|
|
|