PRISM Project #11-1240 (Completed)
Driscoll Island Cold Water Refuge
    Project Details    
Cascade Col Fish Enhance Group; Driscoll Island Cold Water Refuge (#11-1240)

05/23/2012, Attachment #152030, Dirty Water of Smilkameen River on Driscoll Island
Cascade Col Fish Enhance Group; Driscoll Island Cold Water Refuge (#11-1240) 05/23/2012, Attachment #152030, Dirty Water of Smilkameen River on Driscoll Island

Cascade Col Fish Enhance Group; Driscoll Island Cold Water Refuge (#11-1240)

05/23/2012, Attachment #152030, Dirty Water of Smilkameen River on Driscoll Island Cascade Col Fish Enhance Group; Driscoll Island Cold Water Refuge (#11-1240)

Attachment #121242, Driscoll Typ Profile and SectionsCascade Col Fish Enhance Group; Driscoll Island Cold Water Refuge (#11-1240)

Attachment #121243, Driscoll channels plan viewCascade Col Fish Enhance Group; Driscoll Island Cold Water Refuge (#11-1240)

05/23/2012, Attachment #152028, Driscoll Island from HighwayCascade Col Fish Enhance Group; Driscoll Island Cold Water Refuge (#11-1240)

05/23/2012, Attachment #152029, Driscoll 1Cascade Col Fish Enhance Group; Driscoll Island Cold Water Refuge (#11-1240)

05/23/2012, Attachment #152031, Clean water of Okanogan River
Project Status:  Closed Completed since 09/25/2013
 
Project Type:  Planning
Project Sponsor:  Cascade Columbia Fisheries Enhancement Group
Funding Board:  Salmon Recovery Funding Board
              Funding  
Salmon Federal Projects: $42,500
Total RCO Grant: $42,500 (100%)
Total Agreement: $42,500 (100%)
              Links
 

    Project Description    
Water temperatures frequently exceed salmonid preference and survival thresholds in the Okanogan and Similkameen Rivers. Throughout the Okanogan Basin significant efforts are underway to improve tributary habitat for spawning and rearing, increase in-stream flows, and improve upstream water management through negotiations with Canada and the US co-managers. Gains have been made, but high water temperatures remain one of the most significant limiting factors in the Okanogan watershed, particularly from July through September.

The Driscoll Island project presents an opportunity to investigate and design cold water off channel refuge for juvenile salmonids that would be available during a critical time of year when water temperatures often drive juveniles to migrate to less favorable habitats.



    Project Contacts    
         
Project Sponsor: Cascade Columbia Fisheries Enhancement Group Lead Entity: Upper Columbia Salmon Recovery Board Lead Entity
  Project Contact: Jason Lundgren
jason@ccfeg.org
(509) 476-3444
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Amee Bahr
Amee.Bahr@rco.wa.gov
(360) 867-8585
   

    Project Location    
General Area:   Downstream of Oroville
County:   Okanogan
Legislative District:   07
Congressional District 2022:   04
Salmon Recovery Regions:   Upper Columbia River
Watershed Administrative Unit:   Upper Okanogan River
HUC8:   Similkameen (17020007)
WRIA:   Okanogan
Sections:   04
Township:   T39NR27E
Coordinates:   48.90823109
-119.43014383

    Worksites    
Worksite NameScope of WorkActual Planning Cost
Driscoll Island (#1) Conducting habitat restoration scoping and feasibility studies (B.1.b.8), Cultural resources, Preliminary design (B.1.b.11.a RCO) $42,500
 Total$42,500
Amounts may not be complete

    Properties    
Worksite Name Property NameLandowner Type
Driscoll Island (#1)   Property 1 - Driscoll Island State Government
   Total
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricFinal

Restoration Metrics (rolled up from Worksite level)

      
Area Encompassed (acres) (B.0.b.1) 4.0

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 12/08/2011
Data Gathering Started 02/01/2012
RFP Complete/Consultant Hired 02/01/2012
Cultural Resources Complete 03/31/2012 Exempt from DAHP 05-05.
Progress Report Due 07/31/2012
Annual Project Billing Due 07/31/2012
Progress Report Due 01/31/2013
Draft Design to RCO 03/08/2013
Preliminary Design to RCO 06/08/2013
Special Conditions Met 06/08/2013 Appendix D, Preliminary Design Standards.
Final Design to RCO 06/08/2013
Agreement End Date 06/08/2013
Annual Project Billing Due 07/31/2013
Final Report Due 09/08/2013
Final Billing Due 09/08/2013


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State 11-1240 Project Agreement.pdf 03/30/2012
Correspondence Response to RP Comments 06-29-11.doc 06/28/2011
Cost Estimate Driscoll Budget.xls 06/29/2011
Cost Estimate UPDATED May 10 Driscoll Island Budget.xls 05/10/2011
Design document Final Prelim Design Report 05-13.pdf 07/25/2013
Design document Prel Dsgn Fig 2 Driscoll Is GW Wells.pdf 11/07/2012
Design document Prel Dsgn Fig 1 Driscoll Is Site Plan.pdf 11/07/2012
Design document Prel Dsgn Fig 4 Driscoll Is Chnnl 2 Plan.pdf 10/29/2012
Design document Prel Dsgn Fig 3 Driscoll Is Chnnl 1 Plan.pdf 10/29/2012
Design document Fig 5 GW Well Locations 06-06-12.pdf 07/02/2012
Design document Fig 4 Channel 2 X-Section & Profile 06-06-12.pdf 07/02/2012
Design document Fig 2 Channel 2 Plan View 06-06-12.pdf 07/02/2012
Design document Fig 1 Channel 1 Plan View 06-06-12.pdf 07/02/2012
Design document Driscoll channels plan view.jpg 06/29/2011
Design document Driscoll Typ Profile and Sections.jpg 06/29/2011
Final project report Final Report 09/25/2013.pdf 09/25/2013
Landowner acknowledgement form CCFEG Landowner Acknowledgement Form.pdf 05/09/2011
Map Driscoll Island Well Locations Map.pdf 03/14/2011
Map Driscoll Island Vicinity Map.pdf 03/14/2011
Photo Clean water of Okanogan River.jpg 09/07/2012
Photo Dirty Water of Smilkameen River on Driscoll Island.jpg 09/07/2012
Photo Driscoll 1.jpg 09/07/2012
Photo Driscoll Island from Highway.jpg 09/07/2012
Progress report Progress Report 01/14/2013.pdf 01/14/2013
Progress report Progress Report 11/08/2012.pdf 11/08/2012
Progress report Progress Report 07/05/2012.pdf 07/05/2012
Salmon Project Proposal Driscoll Island Final pdf1.pdf 06/30/2011
Salmon Project Proposal Final Driscoll Island Final Proposal.doc 06/29/2011
Salmon Project Proposal Driscoll_Island Trib SRFB Final ver 2.doc 05/10/2011
SRFB Review Panel Comment Form Final Comment Form.docx 12/21/2011
Visuals Okan-Similk Chinook Redds 2014.jpg 05/09/2016
Visuals Okan-Similk Cross Flow Present 11-22.ppt 05/09/2016
Visuals Driscoll Island test well photo series.pdf 05/10/2011
Visuals Driscoll channel locations.pdf 03/18/2011
Visuals Driscoll Island Cold Water Refuge - site visit photos.pdf 03/17/2011