Asotin IMW Monitoring PSMFC 2019
|
    Funding |
  |
Pacific States Projects:
|
$494,357
|
|
Total RCO Grant:
|
$494,357
|
(100%)
|
Total Agreement:
|
$494,357
|
(100%)
|
|
    Links |
  |
|
|
This project is a continuation of the Asotin Creek multi-year IMW project. The project is an Intensively Monitored Watershed monitoring project. The project focuses on three tributaries to the Asotin Creek in Southeast Washington. The tributaries are: Charley Creek, North Fork Asotin Creek, and South Fork Asotin Creek. The purpose of the project is to link salmon and steelhead responses to specific mechanisms related to habitat restoration. The fundamental approach is to treat restoration as an experiment and concentrate a large restoration effort in order to increase the likelihood of detecting a population increase. This type of project will increase our understanding of what restoration activities are most effective, demonstrate how changes in habitat influence survival of various life stages of salmon and steelhead, determine what magnitude of restoration is required to cause a significant population response, and ultimately provide information to better evaluate the efficacy of habitat restoration. The restoration effort is focused on summer run steelhead habitat. The funds for this grant award will focus on continuing the IMW effort in the Asotin. This phase will include: 1) Continue baseline monitoring of 12 permanent sites for fish abundance and habitat condition, 2) Implement restoration treatment plan based on approval of the plan by the Regional Technical Team 3) Monitoring a wide variety of response variables
|
County:
|
|
Asotin
|
Legislative District:
|
|
09
|
Congressional District 2022:
|
|
05
|
Salmon Recovery Regions:
|
|
Snake River
|
Watershed Administrative Unit:
|
|
Middle Snake Agricultural Lands
|
WRIA:
|
|
Middle Snake
|
Coordinates:
|
|
46.32491604 -117.21384199
|
|
|
Worksite Name | Scope of Work | Actual Monitoring and Research Cost |
Asotin (#1)
|
Intensively monitored watershed (E.1.c.15)
|
$494,357
|
| Total | $494,357 |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
Monitoring |
Intensively monitored watershed (E.1.c.15) |
|
# acres (to nearest 0.1 acre) Intensively monitored watershed (E.1.c.15.c)
|
81000.0
|
|
# miles (to nearest 0.01 mile) Intensively monitored watershed (E.1.c.15.a)
|
50.00
|
Milestone Name | Target Date | Description |
Project Start
|
07/01/2019
|
|
Other
|
09/30/2019
|
this project cannot be billed UNTIL resources in 15-1543 are exhausted. which has to open no later than 9/30/19
|
Progress Report Due
|
12/31/2019
|
progress report will be basis for interim semi-annual report for PSMFC, whcih must follow the comment form tempate provided by the SRFB Monitoring Panel
|
Progress Report Due
|
05/31/2021
|
|
Agreement End Date
|
12/01/2021
|
|
Final Report
|
12/31/2021
|
|
Final Billing Due
|
01/31/2022
|
|