Cascade Creek Acquisition
|
San Juan Co Conserv Land Bank; Cascade Creek Acquisition (#15-1300)
Attachment #233765, Cascade Creek
|
|
|
    Funding |
  |
|
    Links |
  |
|
|
The Cascade Creek project on Orcas Island will result in the permanent protection of 23.95 acres of upland forest buffer and riparian corridor that are vital salmon habitat in San Juan County. The Cascade Creek stream system is one of the three most valuable freshwater salmon habitats in San Juan County and has documented historical use by Chinook, Chum, and Coho salmon, and Cutthroat trout. Included in the acquisition request will be 1,250 feet of riparian corridor, including all 300 feet of currently available salmon habitat and 950 feet of upstream buffer habitat that could be opened up for spawning habitat by a proposed fish ladder. The Mountain Lake/Cascade Creek basin extends from the top of Mt. Constitution in Moran State Park through Mountain Lake to Buck Bay, where this project is based. This project, in conjunction with the previously SRFB funded culvert replacement at Cascade Creek (07-1539), will permanently protect and restore this vital salmon habitat.
|
General Area:
|
|
Cascade Creek, Orcas Island.
|
County:
|
|
San Juan
|
Legislative District:
|
|
40
|
Congressional District 2022:
|
|
02
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Orcas Island
|
HUC8:
|
|
San Juan Islands (17110003)
|
WRIA:
|
|
San Juan
|
Sections:
|
|
09
|
Township:
|
|
T36NR01W
|
Coordinates:
|
|
48.62748539 -122.83412656
|
|
|
Worksite Name | Scope of Work |
Cascade Creek Acquisition (#1)
|
Administrative costs (Acq), Appraisal, Appraisal Review, Closing, Recording, Taxes, Title, Land, Stewardship plan
|
| |
Amounts may not be complete
Worksite Name | | Property Name | | Actual Acquisition Acres | Actual Acquisition Cost |
Cascade Creek Acquisition (#1)
|
|
Property 1 - Private Landowner
|
|
23.95
|
$581,000
|
| | | Total | 23.95 | $581,000 |
Amounts may not be complete
Milestone Name | Target Date | Description |
Project Start
|
12/09/2015
|
|
Order Appraisal(s)
|
01/15/2016
|
|
Order Appraisal Review(s)
|
02/29/2016
|
|
Purchase Agreement Signed
|
03/31/2016
|
|
Environmental Assess Complete
|
03/31/2016
|
|
Acquisition Closing
|
05/01/2016
|
|
Progress Report Due
|
05/31/2016
|
|
Recorded Acq Documents to RCO
|
05/31/2016
|
|
Annual Project Billing Due
|
07/31/2016
|
|
Progress Report Due
|
10/31/2016
|
|
Funding Acknowl Sign Posted
|
12/31/2016
|
|
Stewardship Plan to RCO
|
12/31/2016
|
|
Final Report Due
|
01/31/2017
|
|
Final Billing Due
|
02/28/2017
|
|
Progress Report Due
|
04/30/2017
|
|
Annual Project Billing Due
|
07/31/2017
|
|
Progress Report Due
|
10/31/2017
|
|
Agreement End Date
|
12/31/2017
|
|