Bear Creek Reach 6 Restoration - Ph II Design
|
Adopt A Stream Foundation; Bear Creek Reach 6 Restoration - Ph II Design (#15-1059)
Attachment #216471, High Water Looking Upstream
|
|
|
    Funding |
  |
|
    Links |
  |
|
|
The Adopt A Stream Foundation (AASF) is requesting funds to generate preliminary design deliverables focused on improving habitat conditions in a future restoration project. Grant funding will be used to complete preliminary designs (as described in Manual 18 Appendix D-2) for the second phase of stream restoration at the Friendly Village Mobile Home Park in Redmond, WA along Bear Creek Reach 6. AASF will create a Request for Proposals (RFP) and select a qualified consultant that will be responsible for topographic surveying, hydraulic analysis, preliminary and final designs, cultural resource consultation and permitting assistance. AASF will work closely with the consultant and the landowner to develop designs that will provide the maximum benefit to fish and be acceptable to the landowner. The design completed with this current funding request will be used for a future restoration project that will directly address priorities for Bear/Cottage Lake Creeks in the WRIA 8 Conservation Strategy for Chinook salmon (threatened), including protecting and restoring riparian vegetation and floodplain connectivity. This project will address these habitat-limiting factors by focusing design on: installing Large Woody Debris, re-vegetating the riparian buffer, increasing flood plain connectivity and re-establishing stream processes. Stakeholders in the design process include: AASF, WRIA 8, permit agencies, and Friendly Village Park landowner.
|
General Area:
|
|
Bear Creek
|
County:
|
|
King
|
Legislative District:
|
|
48
|
Congressional District 2022:
|
|
01
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Sammamish River
|
HUC8:
|
|
Lake Washington (17110012)
|
WRIA:
|
|
Cedar - Sammamish
|
Sections:
|
|
06
|
Township:
|
|
T25NR06E
|
Coordinates:
|
|
47.68251047 -122.09297632
|
|
|
Worksite Name | Scope of Work | Actual Planning Cost |
Bear Creek Reach 6 (#1)
|
Cultural resources, Preliminary design (B.1.b.11.a RCO)
|
$50,000
|
| Total | $50,000 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Bear Creek Reach 6 (#1)
|
|
Property 1 - Friendly Village Park
|
Private
|
Bear Creek Reach 6 (#1)
|
|
Property 2 - Sewer Line - Owned by Friendly Village
|
Local Government
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
|
|
|
Area Encompassed (acres) (B.0.b.1)
|
1.0
|
|
Miles of Stream and/or Shoreline Affected (B.0.b.2)
|
0.06
|
Milestone Name | Target Date | Description |
Project Start
|
12/09/2015
|
|
Data Gathering Started
|
03/02/2016
|
|
RFP Complete/Consultant Hired
|
03/02/2016
|
|
Progress Report Due
|
06/01/2016
|
|
Annual Project Billing Due
|
06/01/2016
|
|
Cultural Resources Complete
|
07/01/2016
|
|
Progress Report Due
|
10/31/2016
|
|
Draft Design to RCO
|
11/01/2016
|
|
Preliminary Design to RCO
|
12/31/2016
|
|
Final Report Due
|
05/01/2017
|
|
Agreement End Date
|
05/01/2017
|
|
Final Billing Due
|
07/30/2017
|
|