PRISM Project #12-1648 (Completed)
Ninemile Creek Riparian Restoration
    Project Details    
Trout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

05/23/2012, Attachment #161923, Ninemile Creek near Oroville
Trout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648) 05/23/2012, Attachment #161923, Ninemile Creek near Oroville

Trout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

05/23/2012, Attachment #161923, Ninemile Creek near Oroville Trout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

Attachment #146008, Exsisting _CrossingTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

Attachment #151105, DS_HabitatTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

Attachment #151106, Protected reach proposedTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

05/23/2012, Attachment #151167, Aaron Penvose - TU Project ManagerTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

05/23/2012, Attachment #151168, Entrance Road to Eder RanchTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

05/23/2012, Attachment #151170, View to Lake OsoyoosTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

05/23/2012, Attachment #151171, Creek Reach for Riparian RestorationTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

05/23/2012, Attachment #151172, Stream Segment for RestorationTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

05/23/2012, Attachment #151173, Road Crossing Barrier to be CorrectedTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

05/23/2012, Attachment #151174, Upstream Reach for Riparian RestorationTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

05/23/2012, Attachment #151175, Ninemile CreekTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

05/23/2012, Attachment #151176, Irrigation PipelineTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

Attachment #222116, Entrance Sign and Property in Background.Trout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

Attachment #222117, "Culvert"/Tank Removed form Upstream SiteTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

Attachment #222118, New Upstream BR and PIT Tag arrayTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

Attachment #222119, Another New Will, Pump and MeterTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

Attachment #222120, New Lower BridgeTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

Attachment #222121, Ninemile Crk Habitat below lower BridgeTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

Attachment #222122, New Well, Pump and MeterTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

Attachment #222123, Downstream BridgeTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

Attachment #222124, Watering Troughs for Eder & WDFWTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

Attachment #222125, Lower Ninemile Creek HabitatTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

Attachment #222126, Ninemile Crk Reach with Trail CameraTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

Attachment #222127, Deconstructed Water Withdrawl AreaTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

Attachment #222128, Aaron Penvose @ Old Water Withdrawal SiteTrout Unlimited Inc.; Ninemile Creek Riparian Restoration (#12-1648)

Attachment #222129, Upstream BR, Livestock Deterent, PIT Tag
Project Status:  Closed Completed since 07/22/2015
 
Project Type:  Restoration
Project Sponsor:  Trout Unlimited Inc.
Funding Board:  Salmon Recovery Funding Board
              Funding  
Salmon Federal Projects: $152,307
Total RCO Grant: $152,307 (83%)
Sponsor Match: $30,863 (17%)
Total Agreement: $183,170 (100%)
              Links
 

    Project Description    
This project proposes to protect and restore the riparian function of aproximately 1.5 miles of Ninemile Creek, a tributary to Lake Osoyoos and the Okanagon River. Historically, the limiting factor In Ninemile Creek was instream flow restoration, because Ninemile Creek is naturally flow limited and the uppermost surface diversion exsasberabated the problem by withdrawing nearly all surface flow beginning in April annually. In early 2012, in cooperation with the landowner and WDFW, TU secured all surface water flows from the historic surface diversion, effectively creating a natural hydrograph for the basin. Ninemile Creek is unique; the creek is located upriver of Zosel Dam and just south of the US/Canada border, making it the northernmost anadromous tributary in the Okanogan. This project is important because it offers restoration of this unique tributary, where land and water projects have already been completed.
The proposal is to replace the old dilapidated road crossings on the property to improve passage and decrease sedimentation in Ninemile Creek. The third stream crossing on the property will be improved with lower cost technique, a hardened crossing. We believe because this crossing is used less frequently a hard crossing is a better design that will meets the projects objectives; decreased sediment and stream disturbance and provides a suitable location for stock watering with significantly less impact on the resource. The restoraton also includes the installation of over two miles of livestock exclusionary fencing in the riparian area, the removal of hte historic surface water diversion, and watering facility rehabilitation. This restoration benefits ESA-listed steelhead, sockeye and summer/fall Chinook.


    Project Contacts    
         
Project Sponsor: Trout Unlimited Inc. Lead Entity: Upper Columbia Salmon Recovery Board
  Project Contact: Aaron Penvose
apenvose@tu.org
(509) 888-0970
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Amee Bahr
Amee.Bahr@rco.wa.gov
(360) 867-8585
   

    Project Location    
General Area:   North of Oroville, east side of Lake Osoyoos.
County:   Okanogan
Legislative District:   07
Congressional District 2022:   04
Salmon Recovery Regions:   Upper Columbia River
Watershed Administrative Unit:   Tonasket Creek
HUC8:   Okanogan (17020006)
WRIA:   Okanogan
Sections:   12
Township:   T40NR27E
Coordinates:   48.97998405
-119.36930373

    Worksites    
Worksite NameScope of WorkActual Restoration Cost
Ninemile road crossings and fencing (#1) Architectural & Engineering (A&E), Bridge installed or improved (C.2.g.1), Fencing (C.5.d.1), Restoration fencing and gates $183,170
 Total$183,170
Amounts may not be complete

    Properties    
Worksite Name Property NameLandowner Type
Ninemile road crossings and fencing (#1)   Property 1 - Eder property Private
   Total
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricFinal

Restoration Metrics (rolled up from Worksite level)

Riparian Habitat Project
      Fencing (C.5.d.1)
Miles of Fence Along Stream (C.5.d.2) 2.60
Acres of Riparian Area Protected by fencing (C.5.d.3) 15.8

Fish Passage Improvement
      Bridge installed or improved (C.2.g.1)
Miles of stream made accessible by bridge installation/repair (C.2.g.3) 6.00
Number of bridges (C.2.g.2) 2
      
Number of blockages / impediments / barriers impeding passage (C.2.b.4) 2

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 12/06/2012
Preliminary Design to RCO 02/15/2013
Applied for Permits 04/15/2013
Cultural Resources Complete 05/15/2013
Progress Report Due 06/01/2013
Landowner Agreement to RCO 06/17/2013
Permits Complete 07/15/2013
Annual Project Billing Due 07/31/2013
Bid Awarded/Contractor Hired 08/15/2013
Restoration Started 09/01/2013
Progress Report Due 12/01/2013
Progress Report Due 06/01/2014
Annual Project Billing Due 07/31/2014
RCO Final Inspection 04/02/2015
Restoration Complete 06/30/2015
Agreement End Date 06/30/2015
Stewardship Plan to RCO 09/30/2015
Final Report Due 09/30/2015
Final Design to RCO 09/30/2015
Final Billing Due 09/30/2015


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State Agreement.pdf 02/07/2013
Amendment - State 12-1648 Amend #3 Cost Change.pdf 06/05/2015
Amendment - State 12-1648 Amend #1 Cost Change.pdf 11/06/2014
Amendment - State 12-1648 Amend #2 Time Extension.pdf 10/31/2014
Correspondence Review Panel Final Comment Form 10-26-12.docx 01/23/2013
Cost Estimate Eder_Budget_Schedule.xls 06/29/2012
Design document Lower Eder Bridge Design 02-12-13.pdf 05/30/2013
Final project report Final Report 07/22/2015.pdf 07/22/2015
Inspection Photos Final Inspection Photos 04-02-15.pptx 05/05/2015
Inspection Report 05-23-12 Early Application Tour Photos.pptx 08/30/2012
Permit TU - JARPA_WDFW, 5-9-13.pdf 07/20/2015
Permit Updated_Ninemile_Creek_JARPA_ 5-9-13.pdf 05/30/2013
Photo Upstream BR, Livestock Deterent, PIT Tag.jpg 05/05/2015
Photo Aaron Penvose @ Old Water Withdrawal Site.jpg 05/05/2015
Photo Deconstructed Water Withdrawl Area.jpg 05/05/2015
Photo Ninemile Crk Reach with Trail Camera.jpg 05/05/2015
Photo Lower Ninemile Creek Habitat.jpg 05/05/2015
Photo Watering Troughs for Eder & WDFW.jpg 05/05/2015
Photo Downstream Bridge.jpg 05/05/2015
Photo New Well, Pump and Meter.jpg 05/05/2015
Photo Ninemile Crk Habitat below lower Bridge.jpg 05/05/2015
Photo New Lower Bridge.jpg 05/05/2015
Photo Another New Will, Pump and Meter.jpg 05/05/2015
Photo New Upstream BR and PIT Tag array.jpg 05/05/2015
Photo "Culvert"/Tank Removed form Upstream Site.jpg 05/05/2015
Photo Entrance Sign and Property in Background..jpg 05/05/2015
Photo Ninemile Creek near Oroville.jpg 04/19/2013
Photo Irrigation Pipeline.jpg 08/30/2012
Photo Ninemile Creek.jpg 08/30/2012
Photo Upstream Reach for Riparian Restoration.jpg 08/30/2012
Photo Road Crossing Barrier to be Corrected.jpg 08/30/2012
Photo Stream Segment for Restoration.jpg 08/30/2012
Photo Creek Reach for Riparian Restoration.jpg 08/30/2012
Photo View to Lake Osoyoos.jpg 08/30/2012
Photo Entrance Road to Eder Ranch.jpg 08/30/2012
Photo Aaron Penvose - TU Project Manager.jpg 08/30/2012
Photo Protected reach proposed.jpg 08/30/2012
Photo DS_Habitat.jpg 08/30/2012
Progress report Progress Report 12/30/2014.pdf 12/30/2014
Progress report Progress Report 12/20/2013.pdf 12/20/2013
Progress report Progress Report 05/31/2013.pdf 05/31/2013
Salmon Project Proposal Microsoft Word - TU-WWP _ SRFB - Ninemile Riparian Restorati.pdf 06/29/2012
Visuals Exsisting _Crossing.jpg 06/29/2012