Bear Creek Reach 6 Restoration
|
Adopt A Stream Foundation; Bear Creek Reach 6 Restoration (#12-1282)
Attachment #134338, Downstream project area.
|
|
|
    Funding |
  |
|
    Links |
  |
|
|
Adopt A Stream Foundation (AASF) proposes to restore 370 linear feet of Bear Creek located in Friendly Village (18509 NE 95th Street) in the City of Redmond. The proposed project will: 1) convert 0.3 acres of lawn to riparian habitat with 100 new native trees and 500 native shrubs, 2) widen the existing channel cross-section to reduce bank erosion, improve flood capacity, and create space for a seasonal inundated plant community, 3) install large wood to create fish habitat, reduce erosion, and protect existing infrastructure.
AASF is working with the landowners to develop a restoration strategy for the entire property while actively coordinating with the City of Redmond to assure that the work is compatible with future restoration efforts in the reach. Project deliverables will include those listed in Manual 18 Appendixes D-2, D-3 and D-4. This proposal builds upon AASF's work with private property owners in the Bear Creek reach to restore riparian areas, increase in-channel complexity and add large wood. AASF uses King County's 1994 Bear Creek and Evans Creek Capital Improvement Program Projects report to identify potential projects. In particular, restoration is needed throughout Friendly Village development in the downstream end of reach and the equestrian center near the middle of the reach. AASF is currently under contract to scope and design stream restoration for the Friendly Village property owners. Degraded stream habitat conditions are found throughout the property.
|
General Area:
|
|
Bear Creek, Redmond
|
County:
|
|
King
|
Legislative District:
|
|
48
|
Congressional District 2022:
|
|
01
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Sammamish River
|
HUC8:
|
|
Lake Washington (17110012)
|
WRIA:
|
|
Cedar - Sammamish
|
Sections:
|
|
06
|
Township:
|
|
T25NR06E
|
Coordinates:
|
|
47.68287744 -122.09161522
|
|
|
Worksite Name | Scope of Work | Actual Restoration Cost |
Friendly Village (#1)
|
Architectural & Engineering (A&E), Channel reconfiguration and connectivity (C.4.c.1), Cultural resources, Obtain permits, Planting (C.5.c.1), Streambank stabilization (C.4.e.1)
|
$86,774
|
| Total | $86,774 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Friendly Village (#1)
|
|
Property 1 - Friendly Village
|
Private
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
Instream Habitat Project |
Channel reconfiguration and connectivity (C.4.c.1) |
|
Miles of Stream Treated for channel reconfiguration and connectivity (C.4.c.3)
|
0.06
|
|
Miles of Off-Channel Stream Created or Connected (C.4.c.4)
|
0.02
|
|
Acres Of Channel/Off-Channel Connected Or Added (C.4.c.5)
|
0.1
|
|
Instream Pools Created/Added (C.4.c.6)
|
4
|
Streambank stabilization (C.4.e.1) |
|
Miles of Streambank Stabilized (C.4.e.3)
|
0.06
|
Riparian Habitat Project |
Planting (C.5.c.1) |
|
Acres Planted in riparian (C.5.c.3)
|
0.3
|
Permits |
Obtain permits |
|
Number of permits required for implementation of project
|
3
|
Riparian Habitat Project |
Planting (C.5.c.1) |
|
Miles of streambank planted (C.5.c.4)
|
0.07
|
Milestone Name | Target Date | Description |
Project Start
|
12/06/2012
|
Eligible pre-agreement expenses listed in SRFB Manual 18 and Restoration Manual 5
|
Landowner Agreement to RCO
|
04/15/2013
|
For 2013. Will need another is construction deferred until 2014.
|
Progress Report Due
|
05/15/2013
|
|
Cultural Resources Complete
|
06/28/2013
|
CRA circulated to DAHP, Tulalip, Snoqualmie, 7/29/13. Need a Notice to Proceed from RCO
|
Applied for Permits
|
06/28/2013
|
|
Bid Awarded/Contractor Hired
|
06/30/2013
|
To be constructed by Sponsor
|
Annual Project Billing Due
|
07/31/2013
|
|
Preliminary Design to RCO
|
08/30/2013
|
Special Condition B.1, Manual 18 Appendix D-2
|
Progress Report Due
|
11/15/2013
|
|
Progress Report Due
|
05/15/2014
|
|
Permits Complete
|
05/31/2014
|
|
Final Design to RCO
|
05/31/2014
|
Special Condition B.2, Manual 18 Appendix D-3
|
Restoration Started
|
07/01/2014
|
In-Stream Work
|
Restoration Started
|
10/15/2014
|
Riparian Planting
|
Restoration Complete
|
10/31/2014
|
In-Stream
|
Progress Report Due
|
11/15/2014
|
|
Funding Acknowl Sign Posted
|
04/30/2015
|
|
Final Report Due
|
10/30/2015
|
|
Final Design to RCO
|
10/30/2015
|
Special Condition B.3 As-built Design (described in Appendix D-4) (Need Planting Plan)
|
Restoration Complete
|
10/31/2015
|
Riparian Planting
|
Stewardship Plan to RCO
|
11/13/2015
|
NOT REQUIRED
|
RCO Final Inspection
|
11/30/2015
|
Visited in Nov 2014. Final again in 2015.
|
Agreement End Date
|
11/30/2015
|
Project Closing: All expenditures must be incurred before this date. If restoration work is finished early, final invoice and deliverables will be submitted within 3 months of restoration work completion.
|
Final Billing Due
|
01/30/2016
|
Within 2 months of project end date, unless finish ahead of schedule.
|