Skookum Creek RM 6.5 Restoration
|
Project Status:  |
Active since 12/04/2020 |
Planned Completion: |
12/31/2024
This project is in progress. Project scope, activities, and dollars may change.
|
Project Type:  |
Restoration |
  |
|
Funding Board:  |
Salmon Recovery Funding Board
|
    Funding |
  |
|
    RCO Grant Status
|
  |
Total RCO Grant:
|
$266,050.00
|
|
Paid To Date:
|
$252,747.50
|
(95%)
|
Grant Balance:
|
$13,302.50
|
(5%)
|
|
    Links |
  |
|
|
This stream and riparian restoration project includes main-stem, riparian, and off-channel treatments along a ~400 foot reach of Skookum Creek at River Mile (RM) 6.5. While gravel abundance is high within the project reach, there are very few wood pieces that provide gravel retention, pool-formation, and other functions. Wood key pieces and wood clusters will be installed to benefit in-stream processes. Portions of the riparian zone are lacking in conifers and native tree cover, instead shrouded by blackberry and other non-native vegetation. This project includes a riparian weed control and planting plan. A network of groundwater channels on the right-bank of the downstream side of Skookum Creek are known to be used by rearing juvenile salmonids however the condition of this off-channel area has been semi-degraded by reed canary grass, lack of native riparian structure, and a lack of floodplain roughness. We propose to remove reed canary grass sod and to place large wood pieces in strategic locations in the floodplain to provide roughness to maintain the groundwater channels. Additional riparian work will include removing blackberry and reed canary grass thickets and planting native trees and shrubs in the floodplain. The collective project treatments will benefit the egg, juvenile, and adult life stages for coho and chum salmon, and cutthroat trout.
|
General Area:
|
|
Skookum Creek, Mason County, WA
|
County:
|
|
Mason
|
Legislative District:
|
|
35
|
Congressional District 2022:
|
|
06
|
Salmon Recovery Regions:
|
|
Puget Sound
|
Watershed Administrative Unit:
|
|
Mason
|
HUC8:
|
|
Puget Sound (17110019)
|
WRIA:
|
|
Kennedy - Goldsborough
|
Sections:
|
|
28
|
Township:
|
|
T19NR04W
|
Coordinates:
|
|
47.09976586 -123.18498053
|
|
|
Worksite Name | Scope of Work | Proposed Restoration Cost |
Skookum RM 6.5 (#1)
|
Architectural & Engineering (A&E), Channel structure placement (C.4.d.1), Cultural resources, Obtain permits, Planting (C.5.c.1), Riparian Plant removal / control (C.5.h.1)
|
$273,000
|
| Total | $273,000 |
Amounts may not be complete
Worksite Name | | Property Name | Landowner Type |
Skookum RM 6.5 (#1)
|
|
Property 1 - Squaxin Island Tribe (Stewart)
|
Tribal Government
|
| | | Total |
Amounts may not be complete
| Category / Work Type / Metric | Proposed |
Restoration Metrics (rolled up from Worksite level) |
Instream Habitat Project |
Channel structure placement (C.4.d.1) |
|
Miles of Stream Treated for channel structure placement (C.4.d.3)
|
0.10
|
|
Pools Created through channel structure placement (C.4.d.5)
|
2
|
|
Number of structures placed in channel (C.4.d.7)
|
50
|
Riparian Habitat Project |
Planting (C.5.c.1) |
|
Acres Planted in riparian (C.5.c.3)
|
0.5
|
Riparian Plant removal / control (C.5.h.1) |
|
Acres of riparian treated for plant removal/control (C.5.h.3)
|
0.5
|
Planting (C.5.c.1) |
|
Miles of streambank planted (C.5.c.4)
|
0.10
|
Riparian Plant removal / control (C.5.h.1) |
|
Miles of streambank treated for plant removal/control (C.5.h.4)
|
0.05
|
Permit Type | Applied Date | Received Date | Expiration Date | Permit Number |
Dredge/Fill Permit [Section 10/404 or 404]
|
|
|
|
|
Cultural Assessment [Section 106]
|
|
|
|
|
Hydraulics Project Approval [HPA]
|
|
|
|
|
Milestone Name | Target Date | Description |
Project Start
|
09/16/2020
|
|
Progress Report Due
|
08/04/2021
|
|
Progress Report Due
|
08/04/2021
|
|
Cultural Resources Complete
|
10/01/2021
|
Evidence of cultural resources compliance must be submitted to your grants manager, see special condition #1.
|
Annual Project Billing Due
|
12/31/2021
|
|
Final Design to RCO
|
06/30/2022
|
|
Annual Project Billing Due
|
06/30/2022
|
|
Progress Report Due
|
08/31/2022
|
|
Progress Report Due
|
08/31/2022
|
|
Special Conditions Met
|
11/30/2022
|
Special Condition #2: Final designs reviewed and approved by SRFB technical review panel
|
Progress Report Due
|
02/09/2023
|
|
Bid Awarded/Contractor Hired
|
07/01/2023
|
|
Progress Report Due
|
07/05/2023
|
|
Applied for Permits
|
08/15/2023
|
|
Landowner Agreement to RCO
|
12/31/2023
|
|
Progress Report Due
|
02/28/2024
|
|
Annual Project Billing Due
|
06/30/2024
|
|
Permits Complete
|
07/01/2024
|
|
Restoration Started
|
07/15/2024
|
|
Progress Report Due
|
07/30/2024
|
|
RCO Final Inspection
|
09/30/2024
|
|
Final Report Due
|
12/31/2024
|
|
Agreement End Date
|
12/31/2024
|
|
Restoration Complete
|
12/31/2024
|
|
Final Billing Due
|
02/28/2025
|
|
NOTE: This data is subject to change.
Attachment Type | Attachment Title | Attach Date |
Agreement - State
|
20-1090 Agreement .pdf
|
12/04/2020
|
Amendment - State
|
20-1090 Amendment #3 - Time Extension.pdf
|
08/01/2023
|
Amendment - State
|
20-1090 Amendment #2 - Project Name Change.pdf
|
05/26/2023
|
Amendment - State
|
20-1090 Amendment #1 - Project Type Change.pdf
|
08/24/2021
|
Amendment request
|
Skookum Creek RM6.5_Time Extension Request_ July 2023.docx.docx
|
07/28/2023
|
Applicant Resolution/Authorizations
|
SPSSEG RCO Resolution.pdf.pdf
|
02/27/2020
|
Application Review Report
|
Grant Manager Comments Report, 20-1090R(compl 07/28/20 13:01.pdf
|
07/28/2020
|
Application Review Report
|
Grant Manager Comments Report, 20-1090R(rtnd 07/27/20 13:38:.pdf
|
07/27/2020
|
Application Review Report
|
Grant Manager Comments Report, 20-1090R(compl 07/13/20 16:55.pdf
|
07/13/2020
|
Application Review Report
|
Application Review Report, 20-1090R(rtnd 04/09/20 09:00:34).pdf
|
04/09/2020
|
Cost Estimate
|
Stewart RM 6.5 Budget_06242020.xlsx.xlsx
|
06/24/2020
|
Cultural Resources: Formal Consultation
|
2020 SRFB DAHP Consultation.pdf
|
12/08/2020
|
Design document
|
Skookum RM 6.5 Trib - Final Design.pdf.pdf
|
07/05/2023
|
Design document
|
Skookum RM 6.5_Final Designs - 062222.pdf.pdf
|
09/21/2022
|
Design document
|
Skookum RM 6.5 Trib - 90 Percent - 062121.pdf.pdf
|
08/04/2021
|
Design document
|
Skookum - Basis of Design Report - 062121.pdf.pdf
|
08/04/2021
|
Design document
|
Skookum Watershed Summit Summary SPSSEG version (2020-06-17).pdf
|
06/24/2020
|
Design document
|
Preliminary Design Skookum RM 6.5 Trib - 062420.pdf.pdf
|
06/24/2020
|
Design document
|
Skookum Creek - Watershed Plan Base Map - 071118 (3).pdf.pdf
|
06/16/2020
|
Map: Area of Potential Effect (APE)
|
Skookum_RM_6.5 APE.jpg.jpg
|
06/24/2020
|
Map: Restoration Worksite
|
Overview_Project_Map.jpg.jpg
|
02/28/2020
|
Photo
|
IMG_2130.JPG.jpg
|
02/27/2020
|
Photo
|
IMG_2107.JPG.jpg
|
02/27/2020
|
Photo
|
IMG_2090.JPG.jpg
|
02/27/2020
|
Photo
|
IMG_8953.JPG.jpg
|
02/27/2020
|
Photo
|
IMG_8945.JPG.jpg
|
02/27/2020
|
Preliminary design report
|
Preliminary Design Report 062420.pdf.pdf
|
06/24/2020
|
Progress report
|
Progress Report, 20-1090 (accepted 09/06/24 11:39:17).pdf
|
09/06/2024
|
Progress report
|
Progress Report, 20-1090 (accepted 05/09/24 16:47:16).pdf
|
05/09/2024
|
Progress report
|
Progress Report, 20-1090 (accepted 07/28/23 10:45:08).pdf
|
07/28/2023
|
Progress report
|
Progress Report, 20-1090 (accepted 02/10/23 10:07:56).pdf
|
02/10/2023
|
Progress report
|
Progress Report, 20-1090 (accepted 10/06/22 21:49:09).pdf
|
10/06/2022
|
Progress report
|
Progress Report, 20-1090 (accepted 08/13/21 12:25:54).pdf
|
08/13/2021
|
Project Application Report
|
Project Application Report, 20-1090P (sub 10/23/20 08:34:07).pdf
|
10/23/2020
|
Project Application Report
|
Project Application Report, 20-1090R (sub 07/28/20 12:52:37).pdf
|
07/28/2020
|
Project Application Report
|
Project Application Report, 20-1090R (sub 06/24/20 16:32:19).pdf
|
06/24/2020
|
Project Review Comments
|
Proj Review Comments LE, 20-1090P(compl 10/23/20 07:52).pdf
|
10/23/2020
|
Project Review Comments
|
Proj Review Comments Final, 20-1090P(compl 10/23/20 07:52).pdf
|
10/23/2020
|
Project Review Comments
|
Proj Review Comments Initial, 20-1090P(compl 10/23/20 07:52).pdf
|
10/23/2020
|
Project Review Comments
|
Project Review Comments Report, 20-1090R(accepted 07/28/20 1.pdf
|
07/28/2020
|
Project Review Comments
|
Project Review Comments Report, 20-1090R(accepted 07/13/20 1.pdf
|
07/13/2020
|
Visuals
|
FLIR_aerial_skookum_goldsborough_finaldraft.pdf.pdf
|
06/16/2020
|
Visuals
|
Chum Index Escapement.JPG.jpg
|
06/16/2020
|