Skip to main content
Save as PDF
Washington State Recreation and Conservation Office
Project Snapshot
PRISM Project #16-1787 (Completed)
Peshastin Irrigation Pump Exchange Design
    Project Details    
Chelan Co Natural Resource; Peshastin Irrigation Pump Exchange Design (#16-1787)

Attachment #275643, Peshastin Creek
Chelan Co Natural Resource; Peshastin Irrigation Pump Exchange Design (#16-1787) Attachment #275643, Peshastin Creek

Chelan Co Natural Resource; Peshastin Irrigation Pump Exchange Design (#16-1787)

Attachment #275643, Peshastin Creek
Project Status:  Closed Completed since 05/05/2021
 
Project Type:  Planning
Project Sponsor:  Chelan County Natural Resources Department
Funding Board:  Salmon Recovery Funding Board
              Funding  
Salmon Federal Projects: $169,476
Total RCO Grant: $169,476 (85%)
Sponsor Match: $29,908 (15%)
Total Agreement: $199,383 (100%)
              Links
 

    Project Description    
Chelan County will use these funds to work with the Peshastin Irrigation District (PID) to complete preliminary designs for a proposed pump exchange facility that would deliver up to 30 cubic feet per second (cfs) from the Wenatchee River to the Peshastin Irrigation District Canal during late summer critical low flow period. This would allow for a corresponding reduction in diversions from Peshastin Creek, thus increasing instream flow to the lower 2.4 miles of Peshastin Creek and a portion of the Wenatchee River. Increased instream flows in lower Peshastin Creek during the late summer critical low flow period would improve passage conditions for Chinook salmon and bull trout, improve spawning habitat for Chinook salmon, and improve rearing habitat for Chinook salmon, bull trout, and steelhead. An appraisal study was prepared in 2012 to evaluate alternatives for pumping water from the Wenatchee River to the PID Canal. A preferred alternative (Alternative 1) was selected and is the alternative being proposed here. Peshastin Creek is a Priority 2 area with a major spawning population of steelhead, a minor spawning population of Spring Chinook, and a core area for bull trout. The priority action for lower Peshastin Creek is to increase instream flows.

    Project Contacts    
         
Project Sponsor: Chelan County Natural Resources Department Lead Entity: Upper Columbia Salmon Recovery Board Lead Entity
  Project Contact: Michael Kaputa
mike.kaputa@co.chelan.wa.us
(509) 670-6935
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Amee Bahr
Amee.Bahr@rco.wa.gov
(360) 867-8585
   

    Project Location    
County:   Chelan
Legislative District:   12
Congressional District 2022:   08
Salmon Recovery Regions:   Upper Columbia River
Watershed Administrative Unit:   Lower Wenatchee
HUC8:   Wenatchee (17020011)
WRIA:   Wenatchee
Sections:   27
Township:   T24NR18E
Coordinates:   47.54104965
-120.56630729

    Worksites    
Worksite NameScope of WorkActual Planning Cost
Pump Stations on the Wenatchee River (#1) Agency Indirect, Preliminary design (B.1.b.11.a RCO) $199,385
 Total$199,385
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricFinal

Restoration Metrics (rolled up from Worksite level)

      
Area Encompassed (acres) (B.0.b.1) 0.5
Miles of Stream and/or Shoreline Affected (B.0.b.2) 2.40

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 12/07/2016
RFP Complete/Consultant Hired 01/30/2017
Data Gathering Started 04/15/2017
Progress Report Due 07/31/2017
Annual Project Billing Due 07/31/2017
Progress Report Due 12/31/2017
Cultural Resources Complete 09/15/2018 Monitoring of geotech activities required.
Progress Report Due 11/15/2020
Draft Design to RCO 02/26/2021 Draft Conceptual Design (Manual 18, Appendix D-1)
Agreement End Date 03/31/2021
Special Conditions Met 03/31/2021
Final Design to RCO 03/31/2021 Final Conceptual Design (Manual 18, Appendix D-1)
Final Report Due 04/30/2021
Final Billing Due 04/30/2021


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State Agreement 16-1787.pdf 07/13/2017
Amendment - State 16-1787 Amend #7 Time Ext.pdf 06/18/2020
Amendment - State 16-1787 Amend #6 Time Ext.pdf 05/02/2019
Amendment - State 16-1787 Amend #5 Time Ext.pdf 04/19/2019
Amendment - State 16-1787 Amend #4 Special Conds.pdf 04/05/2019
Amendment - State 16-1787 Amend #2 Cost Change.pdf 03/15/2018
Amendment - State 16-1787 Amend #3 Time Ext.pdf 03/01/2018
Amendment - State 16-1787 Amend #1 Cost Change.pdf 07/25/2017
Applicant Resolution/Authorizations SRFB application authorization_Signed.pdf 09/06/2016
Application Review Report Application Review Report, 16-1787P(compl 08/29/16 14:33:58).pdf 08/29/2016
Cost Estimate IPID Pump Exchange - SRFB_Cost_Estimate - 2016-07-01.xlsx 07/01/2016
Design document IPID Value Planning/Engin Study Present 02-10-20.pdf 05/08/2020
Final project report Final Report, 16-1787 (accepted 05/05/21 07:23:04).pdf 05/05/2021
Map: Multi-site and geographic envelope Figure 1 - Potential Pump Station Locations Map.pdf 05/08/2020
Map: Planning Area Figure 2.pdf 08/09/2016
Map: Planning Area Figure 1.pdf 08/09/2016
Photo Peshastin Creek.jpg 08/09/2016
Progress report Draft Icicle Presentation March 2021 3.pptx.pptx 04/23/2021
Progress report Progress Report, 16-1787 (accepted 02/11/21 06:25:31).pdf 02/11/2021
Progress report Progress Report, 16-1787 (accepted 05/08/20 10:34:10).pdf 05/08/2020
Progress report Progress Report, 16-1787 (accepted 04/18/19 13:48:32).pdf 04/18/2019
Progress report Progress Report, 16-1787 (accepted 07/12/18 15:48:12).pdf 07/12/2018
Progress report Progress Report, 16-1787 (accepted 01/09/18 12:49:13).pdf 01/09/2018
Progress report Progress Report, 16-1787 (accepted 08/01/17 20:11:08).pdf 08/01/2017
Project Application Report Application Report, 16-1787P (submitted 08/09/16 14:29:59).pdf 08/09/2016
RCO Fiscal Data Collection Sheet FiscalDataCollectionSheet_2016_proposalPID.pdf 08/09/2016
Salmon Project Proposal IPID Pump Exchange7-1-16CLEAN.pdf 07/01/2016
Salmon Project Proposal IPID Pump Exchange7-1-16TRACK CHANGES.pdf 07/01/2016
Salmon Project Proposal IPID pre-proposalcompiled.pdf 04/15/2016
SRFB Review Panel Comment Form Final SRFB Review Panel Comment Form.pdf 11/09/2016

Back to top Date of last change: 04/16/2024