Skip to main content
Save as PDF
Washington State Recreation and Conservation Office
Project Snapshot
PRISM Project #18-1815 (Other)
Peshastin Creek Barrier Removal
    Project Details    
Project Status:  Wastebasket since 12/19/2018
 
Project Type:  Restoration
Project Sponsor:  Chelan County Natural Resources Department
Funding Board:  Salmon Recovery Funding Board
              Funding  
Salmon State Projects: $205,000
Total RCO Grant: $205,000 (84%)
Sponsor Match: $40,000 (16%)
Total Agreement: $245,000 (100%)
              Links
 

    Project Description    
This project will remove a partial fish passage barrier culvert from Peshastin Creek (near RM 15.5) and replace it with a bridge under Scotty Creek road, improving fish passage for steelhead in the upper Peshastin and Scotty Creek. Once completed this project will improve passage to 3.5 miles of habitat.

    Project Contacts    
         
Project Sponsor: Chelan County Natural Resources Department Lead Entity: Upper Columbia Salmon Recovery Board Lead Entity
  Project Contact: Jennifer Hadersberger
jennifer@cdlandtrust.org
(509) 860-1022
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Amee Bahr
Amee.Bahr@rco.wa.gov
(360) 867-8585
   

    Project Location    
County:   Chelan
Legislative District:   12
Congressional District 2022:   08
Salmon Recovery Regions:   Upper Columbia River
Watershed Administrative Unit:   Blewett
HUC8:   Wenatchee (17020011)
WRIA:   Wenatchee
Sections:   24
Township:   T22NR17E
Coordinates:   47.38601964
-120.65806325

    Worksites    
Worksite NameScope of WorkProposed Restoration Cost
Peshastin creek RM 15.5 (#1) Agency Indirect, Architectural & Engineering (A&E), Bridge installed or improved (C.2.g.1), Cultural resources, Obtain permits $245,000
 Total$245,000
Amounts may not be complete

    Properties    
Worksite Name Property NameLandowner Type
Peshastin creek RM 15.5 (#1)   Property 1 - Peshastin creek RM 15.5 Federal Government
   Total
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricEstimated

Restoration Metrics (rolled up from Worksite level)

Permits
      Obtain permits
Number of permits required for implementation of project 4

Fish Passage Improvement
      Bridge installed or improved (C.2.g.1)
Miles of stream made accessible by bridge installation/repair (C.2.g.3) 3.50
Number of bridges (C.2.g.2) 1
      
Number of blockages / impediments / barriers impeding passage (C.2.b.4) 1

    Project Permits    
Permit TypeApplied
Date
Received
Date
Expiration
Date
Permit Number
Nationwide Permit
Hydraulics Project Approval [HPA]

    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Applicant Resolution/Authorizations SRFB application authorization form.pdf.pdf 08/08/2018
Application Review Report Application Review Report, 18-1815R(compl 08/27/18 09:02:46).pdf 08/27/2018
Cost Estimate SRFB_Cost_Estimate.xlsx.xlsx 08/08/2018
Design document 2015Design.pdf.pdf 08/08/2018
Map: Restoration Worksite locationmap.pdf.pdf 08/08/2018
Photo IMG_3198.jpg.jpg 08/08/2018
Project Application Report Application Report, 18-1815R (submitted 08/09/18 09:55:36).pdf 08/09/2018
Salmon Project Proposal UpperPeshastinBarrierAugustFinalproposal.pdf.pdf 08/09/2018
SRFB Review Panel Comment Form 18-1815 Peshastin Creek Barrier Removal.pdf 12/28/2018

Back to top Date of last change: 10/15/2024