WDFW Asotin IMW (Fi-Fo) - PSMFC
|
    Funding |
  |
Pacific States Projects:
|
$76,045
|
|
Total RCO Grant:
|
$76,045
|
(100%)
|
Total Agreement:
|
$76,045
|
(100%)
|
|
    Links |
  |
|
|
The work plan for the Asotin IMW will include the following services provided by WDFW: 1. Coordinate juvenile fish tagging in the summer (July) and fall (Sept/Oct); manage crew of 3-6 people and gear 2. Provide two technicians to assist in stream habitat sampling mostly from mid July to late September. The crew may be required to attend CHaMP training in early June 3. Monitor and maintain as needed the Array Infrastructure in Asotin Creek; any new equipment will be purchased with IMW funds if available 4. Assist in other IMW tasks as needed and agreed upon, including restoration, temperature and discharge monitoring, mobile fish surveys, etc.
|
County:
|
|
Asotin
|
Legislative District:
|
|
09
|
Congressional District 2022:
|
|
05
|
Salmon Recovery Regions:
|
|
Snake River
|
Watershed Administrative Unit:
|
|
Grande Ronde
|
WRIA:
|
|
Middle Snake
|
Coordinates:
|
|
46.07102504 -117.20922893
|
|
|
Worksite Name | Scope of Work | Actual Monitoring Cost |
Asotin (#1)
|
Salmonid smolt or fry monitoring (E.1.c.2)
|
$76,045
|
| Total | $76,045 |
Amounts may not be complete
| Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
Monitoring |
Salmonid smolt or fry monitoring (E.1.c.2) |
|
# miles (to nearest 0.01 mile) monitored for Salmonid smolt or fry (E.1.c.2.a)
|
20.00
|
Milestone Name | Target Date | Description |
Project Start
|
10/01/2013
|
|
Progress Report Due
|
04/30/2014
|
This report forms the basis for PSFMC reporting see
|
Progress Report Due
|
09/30/2014
|
This is the end of the project period but due to the field calendar a no-cost time extension may be requested
|
Progress Report Due
|
11/30/2014
|
|
Agreement End Date
|
12/31/2014
|
|
Final Billing Due
|
01/31/2015
|
|
Final Report
|
01/31/2015
|
|