Washington State Recreation and Conservation Office
Project Snapshot
PRISM Project #06-2249 (Completed)
Alder Creek Culvert #1
    Project Details    
Chelan Co Natural Resource; Alder Creek Culvert #1 (#06-2249)

04/30/2008, Attachment #60001, Upstream of Culvert
Chelan Co Natural Resource; Alder Creek Culvert #1 (#06-2249) 04/30/2008, Attachment #60001, Upstream of Culvert

Chelan Co Natural Resource; Alder Creek Culvert #1 (#06-2249)

04/30/2008, Attachment #60001, Upstream of Culvert Chelan Co Natural Resource; Alder Creek Culvert #1 (#06-2249)

04/30/2008, Attachment #60000, Culvert InletChelan Co Natural Resource; Alder Creek Culvert #1 (#06-2249)

04/30/2008, Attachment #60002, Upstream Rock WeirsChelan Co Natural Resource; Alder Creek Culvert #1 (#06-2249)

04/30/2008, Attachment #60003, Culvert OutletChelan Co Natural Resource; Alder Creek Culvert #1 (#06-2249)

04/30/2008, Attachment #60005, Alder Creek CulvertChelan Co Natural Resource; Alder Creek Culvert #1 (#06-2249)

09/09/2013, Attachment #173141, Alder Creek SignChelan Co Natural Resource; Alder Creek Culvert #1 (#06-2249)

09/09/2013, Attachment #173142, Upstream Rock Weirs 1Chelan Co Natural Resource; Alder Creek Culvert #1 (#06-2249)

09/09/2013, Attachment #173143, Rock Weirs & Culvert InletChelan Co Natural Resource; Alder Creek Culvert #1 (#06-2249)

09/09/2013, Attachment #173145, Culvert Outlet and Rock Weir
Project Status:  Closed Completed since 06/03/2008
 
Project Type:  Restoration
Project Sponsor:  Chelan County Natural Resources Department
Funding Board:  Salmon Recovery Funding Board
              Funding  
Salmon Federal Projects: $315,500
Total RCO Grant: $315,500 (85%)
Sponsor Match: $56,000 (15%)
Total Agreement: $371,500 (100%)
              Links
 

    Project Description    
One fish passage barrier culvert (Alder #1) will be replaced with a modular steel bridge to provide year-round fish passage to all species at all life stages. In addition to the barrier correction, the riparian area will be planted to restore and enhance habitat. Based on the Upper Columbia Regional Technical Team's project proposal reviews on August 18, 2006 the Chelan County Natural Resource Department has asked the Bureau of Reclamation to analyze Alder Creek Culvert #1 for the possibility of retrofitting this culvert. If a retrofit alternative is feasible, it will be sent to the funding source for review prior to implementation. A retrofit alternative would reduce the project cost.

    Project Contacts    
         
Project Sponsor: Chelan County Natural Resources Department Lead Entity: Upper Columbia Salmon Recovery Board Lead Entity
  Project Contact: Paul Heffernan
Paul.Heffernan@co.chelan.wa.us
(509) 667-6346
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Amee Bahr
Amee.Bahr@rco.wa.gov
(360) 867-8585
   

    Project Location    
General Area:   Alder Creek, tributary of the Chiwawa River
Waterbody:   Alder Creek, Alder Creek, triburary of the Chiwawa, Chiwawa River
County:   Chelan
Legislative District:   12
Congressional District 2022:   08
Salmon Recovery Regions:   Upper Columbia River
Watershed Administrative Unit:   Lower Chiwawa
HUC8:   Wenatchee (17020011)
WRIA:   Wenatchee
Sections:   12
Township:   T27NR17E
Coordinates:   47.84829459
-120.65876370

    Worksites    
Worksite NameScope of WorkActual Restoration Cost
Alder Creek Culvert #1 (#1) Architectural & Engineering (A&E), Channel structure placement (C.4.d.1), Culvert installed or improved (C.2.f.1), Fish passage blockages removed or altered (C.2.c.1), Fishway chutes or pools installed (C.2.d.1), Restoration signs, Traffic control, Utility relocation / reconnection $375,136
 Total$375,136
Amounts may not be complete

    Properties    
Worksite Name Property NameLandowner Type
Alder Creek Culvert #1 (#1)   Property 1 - Property - Worksite #1 Local Government
   Total
Amounts may not be complete

    Project Metrics (Outcomes, Benefits)    
 Category / Work Type / MetricFinal

Restoration Metrics (rolled up from Worksite level)

Instream Habitat Project
      Channel structure placement (C.4.d.1)
Miles of Stream Treated for channel structure placement (C.4.d.3) 0.01
Acres Of Streambed Treated for channel structure placement (C.4.d.4) 0.1
Pools Created through channel structure placement (C.4.d.5) 10
Number of structures placed in channel (C.4.d.7) 10

Fish Passage Improvement
      
Number of blockages / impediments / barriers impeding passage (C.2.b.4) 2

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 12/20/2006 Project design (BOR)
Applied for Permits 02/01/2007 Submit JARPA & SPIF
Bid Awarded/Consultant Hired 07/01/2007 Contract awarded
Construction Started 07/15/2007 Pre-con/mobilization
Annual Project Billing Due 07/15/2007 Annual billing required by July 15th of each year of project
Construction Complete 09/30/2007 Earthwork-structure
Agreement End Date 12/30/2007 All revegetation complete
Final Docs/Billing to Mgmt Agy 01/30/2008 Submittal of all invoices


    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State Project Agreement 6-25-07.pdf 09/10/2007
Application authorization Application Authorization Memo.pdf 10/10/2006
Correspondence WDFW Fish Passage Evaluation.pdf 10/04/2006
Evaluation proposal Evaluation Proposal.pdf 09/18/2006
Final project report Final Report 4-30-08.pdf 06/02/2008
Inspection Report Compliance Inspection Photos 09-09-13.pptx 10/03/2013
Map Map.pdf 06/30/2008
Photo Culvert Outlet and Rock Weir.jpg 10/03/2013
Photo Rock Weirs & Culvert Inlet.jpg 10/03/2013
Photo Upstream Rock Weirs 1.jpg 10/03/2013
Photo Alder Creek Sign.jpg 10/03/2013
Photo Alder Creek Culvert.jpg 06/02/2008
Photo Culvert Outlet.jpg 06/02/2008
Photo Upstream Rock Weirs.jpg 06/02/2008
Photo Upstream of Culvert.jpg 06/02/2008
Photo Culvert Inlet.jpg 06/02/2008
Project presentation Grant Application.pdf 09/18/2006
WDFW barrier & screening forms BEF & Cost Estimates.pdf 09/18/2006

Back to top Date of last change: 02/05/2024